Building Update 1/26/2009
On Friday 1/23 the footers were poured. The inspector found everything in prder on Thursday and we got a real break in the weather, after having snow on Tuesday. Friday and the weekend were perfect days for pouring and curing concrete. It reached 60 Friday and as of Monday 1/26, we have not had any temperatures below freezing. The concrete has cured well enough that freezing is not a concern, now. 750 concrete blocks were delivered today and after 2 days of possible rain, the masons should be starting the retaining wall portion of the foundation, this week. When we fill the blocks with grout, we will be forming the building piers and placing the bolts in the concrete to attach the building steel. With a little cooperation from the weather, we should have a shell of a building up by mid to late February!