Building Update March 11th, 2009
The floor was finished on Thursday 2/26/09. It was perfect day for concrete. Sunny, slightly breezy and mid sixty degrees. Roosevelt and his 8 man crew did a superb job of finishing the 106 yards of concrete. 6000 sq. ft of floor. The concrete was pumped by a huge concrete pumping truck capable to reaching out 34 meters. 11 concrete delivery trucks rolled in and out for about 3 1/2 hours. here is a picture of the truck with the boom sections sticking up.

Part of floor poured, remaining portion with plumbing drains and vents stubbed up for later.
Floor after finishing.

Floor with light gray sealer applied, ready for steel.
The erectors arrived 3/10 to begin putting up the steel building. As of 3/11. most of the "red iron" has been put together. here are a few early shots of the steel skeleton. The view from the Route 27 end of the street is pretty impressive. "You can't miss it, once you turn onto Joshua Court!"

From the corner of Joshua Ct. and Rt. 27

Steel after one day of erecting.

Looking from the cul-de-sac end of Joshua Court.

Part of floor poured, remaining portion with plumbing drains and vents stubbed up for later.
Floor after finishing.

Floor with light gray sealer applied, ready for steel.
The erectors arrived 3/10 to begin putting up the steel building. As of 3/11. most of the "red iron" has been put together. here are a few early shots of the steel skeleton. The view from the Route 27 end of the street is pretty impressive. "You can't miss it, once you turn onto Joshua Court!"

From the corner of Joshua Ct. and Rt. 27

Steel after one day of erecting.

Looking from the cul-de-sac end of Joshua Court.



Comments